Announced means there’s a press release, but only about 3 to 10% of those projects actually happen. Requested is when someone files an application with the utility, and just 2 to 8% of those move forward.
Contracted means someone has signed a deal that would cost money to cancel, so 50 to 78% of these go ahead. Energized is when the project is actually connected to the grid. Only this last stage is truly a gigawatt.
Almost every headline you read sits in the first two rows.
A national lab studied every project that entered the U.S. queue from 2000 to 2020. Only about 13% made it to operation, while three quarters were withdrawn.
Full framework in today’s post.