NEXTDC had a customer, a contract and data halls under construction. It lacked the power line.

22 Oct 2026 1 min read

On 21 October, the Australian data center operator said Jemena, the local electricity network, had suspended parts of the 66kV line works for its M3 Melbourne campus after community and stakeholder opposition. Jemena does not expect to restart them before February 2027, so the next increase in grid supply slips to the 2028 financial year.

NEXTDC cut its FY27 underlying EBITDA guidance to A$245 million to A$265 million, from A$385 million to A$410 million, about 36 percent lower at the midpoint. It put all new development projects and land purchases on hold. The shares fell 41.7 percent in a day, to A$5.35.

Our read: in AI infrastructure, the moat is the energized megawatt. Contracts, customers and buildings can all be ready and still earn nothing until the grid delivers. That risk sits with local councils and network operators, and no order book shows it.

The part to watch is financing. NEXTDC has A$8.7 billion of liquidity, but it says its ability to draw its undrawn senior debt depends on when new contracts start billing, and that delays at M3 could change that.

Research, not advice.

Go deeper

Explore the research library

Company, industry and market reports with sources, charts, possible outcomes and the full evidence.

Free

More free explainers

Markets, companies, portfolio basics and investing foundations. All free articles.

Back to Learn