On 24 September, after Oracle’s force majeure notice on its New Mexico campus was reported, shares in Oracle, Blue Owl and Bloom Energy all closed between 3.1 and 3.7 percent lower. To see who pays if a data center runs late, read the contracts.
At Project Jupiter, Oracle cannot end the lease, pays the debt costs and is responsible for power, according to a person familiar with the matter who spoke to Reuters. Power is the part at risk: the gas line’s target has moved from August 2026 to February 2027, while Oracle says the campus is still on schedule.
Google can walk away from its SpaceX compute contract if the GPUs aren’t delivered by 30 September, after a month’s grace. After 31 December either side can leave on 90 days’ notice. Meta leased its Hyperion campus for an initial four years, with options to extend. In Illinois, the developer of a 1.8-gigawatt campus says a $1.00 letter of credit met the first security test in its grid agreement. ComEd tried to cancel, FERC said no, and a federal court will decide the $1 question.
Oracle has $288bn of leases signed but not started, running 15 to 19 years, against a backlog it expects to recognize mostly within five.
On our reading, the buyers kept ways out. When a data center is late, someone still pays: whoever can’t leave.
Get the Weekly Explainer
The biggest market story explained, every week. Free, by email.
Read the complete Member report
Sources, charts, possible outcomes and the full evidence behind this article.
Then $19/month. Cancel online before the trial ends.
More free explainers
Markets, companies, portfolio basics and investing foundations. All free articles.
Back to Learn